EMERGENCY DEPARTMENT FAST TRACK

NEWARK BETH ISRAEL MEDICAL CENTER

Converted part of the existing Emergency Department into a new fast track emergency area to meet the hospital’s desire to treat patients more efficiently and effectively. Work included custom millwork cabinets and counters, new light fixtures, plumbing, HVAC, sprinklers and floor, ceiling and wall finishes. The project was completed in eight weeks while the space was occupied and operational.

SERVICES PROVIDED

General Construction

COMPLETION DATE

February 2006

COST

$2,000,000

ARCHITECT

S/L/A/M Architects PC
80 Glastonbury Boulevard
Glastonbury, Connecticut 06033

OWNER

Newark Beth Israel Medical Center
201 Lyons Avenue
Newark, NJ 07112

1/9